Laurel Mountain Hybrid had a generating capacity of 97.6 MW on 2025.
claim · revision 1 · immutable k_21620cd9186c9bfc08feeb1f50db50a3 · asserted · current · positive · confidence 0.95 tier_default/v1
| subject | laurel-mountain-hybrid |
|---|---|
| predicate | generating_capacity |
| object / value | {"amount":97.6,"unit":"MW"} quantity |
| valid time | 2025 → open current |
| asserted / retrieved | 2026-11-24T00:00:00Z / 2026-11-23T19:24:05Z |
| revisions | @1 2026-11-24 |
Evidence
57447,Laurel Mountain Hybrid,61012,AES Distributed Energy,Belington,WV,Barbour,39.007199999999997,-79.886600000000001,RFC,PJM,"PJM Interconnection, LLC",IPP Non-CHP,97.6,Onshore Wind Turbine,Onshore Wind Turbine,S
retrieved 2026-11-23T19:24:05Z · capture ev/f1d862356710 · line:3178 · rights: public-record (EIA-860 Annual Electric Generator Report (public domain, U.S. Government)) display yes · export yes · train yes